An iconic office development with a high pressure radiator solution to stand the test of time.
The Challenge
The height of the building places high pressure on the LPHW system. These pressures would be too great for a standard tubular steel radiator. We used a high pressure radiator solution with 2mm steel wall thickness to ensure no leaks or deformations would occur over time. This strategy proved very successful on the project.
The Solution
We provided Runtal radiators throughout this iconic office development. We worked closely with the client and design team to find a solution that would stand the test of time.